Electric utility lines and telecommunication lines: This NWP authorizes discharges of dredged or fill material into waters of the United States and ...
Mar 15, 2021 · Electric utility lines and telecommunication lines: This NWP authorizes discharges of dredged or fill material into waters of the United ...
People also ask
What is NWP 58 utility line activities for water and other substances?
Nationwide Permit 58 - Utility Line Activities for Water and Other Substances. Activities required for the construction, maintenance, repair, and removal of utility lines for water and other substances, excluding oil, natural gas, products derived from oil or natural gas, and electricity.
What are nationwide permits USACE?
What is a Nationwide Permit? A Nationwide Permit (NWP) is a type of general permit that is issued every five years by the U.S. Army Corps of Engineers (Corps), for specific activities that have no more than minimal individual and cumulative adverse effects to the aquatic environment.
What is nationwide permit 12?
NWP 12 for above and below ground utility lines is probably the most commonly used nationwide permit. In the US, every oil or natural gas pipeline, electric transmission line, fiber optic line, stormwater pipe, sewer line, etc., relies on NWP 12.
What is a wetland U.S. Army Corps of Engineers?
Wetlands are transitional areas between open water and dry land and are often found along bays, lakes, rivers and streams. Some are drier than others and may have standing water or saturated soil conditions only during part of the year.
... NATIONWIDE PERMIT (NWP) PRE-CONSTRUCTION NOTIFICATION (PCN) ... 2021 Nationwide Permit 57 – Final Decision Document ... NOAA Fisheries Final Endangered Species Act ...
Mar 15, 2021 · Electric utility lines and telecommunication lines: This NWP authorizes discharges of dredged or fill material into waters of the United ...